Research API-first approach with Spring Boot (openapi-generator-maven-plugin)
and Vue 3 frontend (openapi-typescript + openapi-fetch). Add T-5 setup task
for scaffolding the tooling. Update T-4 to depend on T-5 (removes redundant
API client AC), update implementation phases table and mermaid dependency graph.

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-03-04 17:46:48 +01:00

160 lines
8.4 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# Implementation Phases
A recommended implementation order based on the dependency graph across all stories and setup tasks.
## Phase 0: Project Infrastructure
All setup tasks must complete before any user story work begins. T-3 can run in parallel with Phase 1.
| Order | Task | Depends on | Notes |
|-------|------|------------|-------|
| 1 | T-1: Initialize monorepo structure | — | Scaffolds empty backend + frontend projects |
| 2 | T-2: Deployment setup (Dockerfile + config) | T-1 | Docker build, DB connection, health check |
| 2* | T-5: API-first tooling setup | T-1 | OpenAPI spec, codegen plugins, generated types — parallelizable with T-2 |
| 3 | T-4: Development infrastructure | T-2, T-5 | Migrations, router, test infra — gates all user stories |
| 3* | T-3: CI/CD pipeline | T-1, T-2 | Parallelizable with T-4. Uses Gitea Actions (per Q-5 resolution) |
## Phase 1: Core Event Flow (Vertical Slice)
The end-to-end journey from creating an event to viewing it to RSVPing. US-1 is the "Durchstich" that bootstraps the full stack (DB table, backend endpoint, frontend form, localStorage, routing). It will take significantly longer than subsequent stories.
| Order | Story | Depends on | Parallelizable |
|-------|-------|------------|----------------|
| 1 | US-1: Create an event | T-4 | — |
| 2 | US-2: View event landing page | US-1 | — |
| 3 | US-3: RSVP to an event | US-2 | — |
These three stories are strictly sequential. No parallelization within this phase.
## Phase 2: Organizer Management & Event Lifecycle
All stories in this phase depend on US-1 (and T-4 transitively). They can be implemented in parallel since they are independent of each other. Some are more useful after Phase 1 completes (e.g. US-4 needs RSVPs to manage), but they are structurally implementable after US-1.
| Story | Depends on | Notes |
|-------|------------|-------|
| US-4: Manage guest list | US-1 | Most useful after US-3 provides RSVPs to manage |
| US-5: Edit event details | US-1 | Required by US-9 in Phase 3 |
| US-18: Cancel an event | US-1 | Enables deferred ACs in US-2, US-3, US-8 |
| US-19: Delete an event | US-1 | Enables deferred AC in US-2 |
| US-12: Automatic data deletion after expiry | US-1 | Enables deferred AC in US-2; server-side scheduled job |
| US-13: Limit active events | US-1 | Server-side config; independent of all other stories |
**Recommended order within phase:** US-5, US-4, US-18, US-19, US-12, US-13 — starting with US-5 because US-9 (Phase 3) depends on it, and US-4 because it completes the organizer toolset around RSVPs.
## Phase 3: Enhanced Event Page Features
Features that enrich the event page for guests. Most depend on US-2 (event page exists). US-9 additionally requires US-5 (editing). US-10b requires US-10a.
| Story | Depends on | Parallelizable with |
|-------|------------|---------------------|
| US-6: Bookmark an event | US-2 | US-8, US-10a, US-11 |
| US-8: Add event to calendar (.ics / webcal) | US-2 | US-6, US-10a, US-11 |
| US-9: Highlight changed event details | US-2, US-5 | US-6, US-8, US-10a, US-11 (if US-5 is done) |
| US-10a: Post update messages | US-1, US-2 | US-6, US-8, US-11 |
| US-10b: New-update indicator | US-10a | Must follow US-10a |
| US-11: Generate QR code | US-2 | US-6, US-8, US-10a |
**Recommended order within phase:** US-6, US-8, US-11 (simple, independent), then US-10a → US-10b (sequential pair), then US-9 (requires US-5 from Phase 2).
## Phase 4: Visual Customization
Event-level theming and image selection. Both depend on US-1 and US-2. US-15 and US-16 are independent of each other but share the event creation/editing form surface area, so coordinating them is beneficial.
| Story | Depends on | Notes |
|-------|------------|-------|
| US-15: Choose event color theme | US-1, US-2 | Predefined theme picker in creation/edit forms |
| US-16: Select header image from Unsplash | US-1, US-2 | Optional feature gated by API key config |
**Recommended order:** US-15 first (simpler, no external dependency), then US-16. Consider the interaction between event themes and dark/light mode (US-17) — implement US-17 before or alongside US-15 if possible.
## Phase 5: App Shell & PWA
Client-side infrastructure and app-level UX features. These have no or minimal structural dependencies but are only meaningfully testable after earlier phases provide content and data.
| Story | Depends on | Practically useful after |
|-------|------------|------------------------|
| US-7: Local event overview | None (structural) | US-1, US-3, US-6 populate localStorage |
| US-14: Install as PWA | T-4 (structural) | US-2, US-7 provide pages to cache |
| US-17: Dark/light mode | None (structural) | T-4 provides frontend scaffold |
**Recommended order:** US-17 (can be started early once the frontend scaffold exists — consider implementing alongside Phase 2 or 3), then US-7 (after localStorage-populating stories are available), then US-14 (after the app has real pages and assets).
**Note on US-17 timing:** US-17 is listed in Phase 5 for logical grouping, but it can be implemented as early as Phase 2 since it only needs the frontend scaffold. Implementing it earlier is recommended because US-15 (Phase 4) must consider the interaction between event color themes and dark/light mode. Having dark/light mode in place before US-15 simplifies that work.
## Deferred Acceptance Criteria
Several stories contain ACs that reference features from later phases. These are marked `[deferred until US-X is implemented]` in the story text:
| Story | AC | Deferred until | Phase unlocked |
|-------|-----|---------------|----------------|
| US-2 AC 5 | Cancelled state display | US-18 | Phase 2 |
| US-2 AC 6 | Event not found (expiry deletion) | US-12 | Phase 2 |
| US-2 AC 6 | Event not found (organizer deletion) | US-19 | Phase 2 |
| US-3 AC 11 | RSVP blocked on cancelled event | US-18 | Phase 2 |
| US-8 AC 9 | STATUS:CANCELLED in .ics | US-18 | Phase 2 |
| US-12 AC 2 | Delete stored header images | US-16 | Phase 4 |
Once the referenced story is implemented, revisit the deferring story to activate the deferred AC.
## Dependency Graph
Render this diagram at [mermaid.live](https://mermaid.live) or view it directly in Gitea (which renders `mermaid` blocks natively).
```mermaid
graph TD
classDef infra fill:#4a90d9,stroke:#2c5f8a,color:#fff
classDef core fill:#e8a838,stroke:#b07c1e,color:#fff
classDef organizer fill:#50b86c,stroke:#2d8043,color:#fff
classDef enhanced fill:#9b59b6,stroke:#6c3483,color:#fff
classDef visual fill:#e74c3c,stroke:#a93226,color:#fff
classDef shell fill:#7f8c8d,stroke:#566566,color:#fff
%% Phase 0: Infrastructure
T1(["T-1: Monorepo"]):::infra --> T2(["T-2: Docker & DB"]):::infra
T1 --> T5(["T-5: API-First Tooling"]):::infra
T2 --> T4(["T-4: Dev Infra"]):::infra
T5 --> T4
T2 --> T3(["T-3: CI/CD"]):::infra
%% Phase 1: Core Event Flow
T4 --> US1["US-1: Create Event"]:::core
US1 --> US2["US-2: View Event"]:::core
US2 --> US3["US-3: RSVP"]:::core
%% Phase 2: Organizer & Lifecycle (branch from US-1)
US1 --> US4["US-4: Guest List"]:::organizer
US1 --> US5["US-5: Edit Event"]:::organizer
US1 --> US18["US-18: Cancel"]:::organizer
US1 --> US19["US-19: Delete"]:::organizer
US1 --> US12["US-12: Auto-Cleanup"]:::organizer
US1 --> US13["US-13: Event Limit"]:::organizer
%% Phase 3: Enhanced Features (branch from US-2)
US2 --> US6["US-6: Bookmark"]:::enhanced
US2 --> US8["US-8: Calendar .ics"]:::enhanced
US2 --> US10a["US-10a: Messages"]:::enhanced
US2 --> US11["US-11: QR Code"]:::enhanced
US5 --> US9["US-9: Change Highlights"]:::enhanced
US2 --> US9
US10a --> US10b["US-10b: New-Update Badge"]:::enhanced
%% Phase 4: Visual Customization (branch from US-2)
US2 --> US15["US-15: Color Themes"]:::visual
US2 --> US16["US-16: Unsplash Images"]:::visual
%% Phase 5: App Shell & PWA
T4 --> US14["US-14: PWA"]:::shell
US7["US-7: Local Overview"]:::shell
US17["US-17: Dark/Light Mode"]:::shell
```
**Legend:**
- 🔵 Infrastructure (T-1 T-5)
- 🟠 Core Event Flow (US-1 US-3)
- 🟢 Organizer & Lifecycle (US-4, US-5, US-12, US-13, US-18, US-19)
- 🟣 Enhanced Features (US-6, US-8 US-11)
- 🔴 Visual Customization (US-15, US-16)
- ⚪ App Shell & PWA (US-7, US-14, US-17)
US-7 and US-17 appear as isolated nodes — they have no structural dependencies but are only practically useful after earlier phases provide content (see Phase 5 notes above).